Quotation

Raft slabs and drainage, Units 1, 2 and 3, 14 Newark Street, Port Glasgow

Vortex Scotland Ltd
14 Newark Street, Port Glasgow

Where we’re working

Map of the site location
14 Newark StreetPort Glasgow · Units 1, 2 and 3
Target // locked
Vortex Scotland Ltd
55.93212° N
4.67887° W
100 m
N▲
© OpenStreetMap contributors

Option A or Option B

Both options finish in the same place: two raft slabs with their thickened edge beams, power floated and ready for the steel, and the drainage to Dougall Baillie's layout. The difference is who does the groundwork before the concrete goes in.

Option A

We do it all
£254,100 plus VAT

We strip the site, clear the stockpile over Unit 3, dig the edge beams, lay and roll the Type 1, lay the drainage alongside, then pour both slabs.

  • One contractor and one programme, about 24 working days
  • We prepare the ground under the slabs; soft spots and extra fill are at the agreed rates
  • Three invoices

Option B

Your groundworker does the earthworks
£195,000 plus VAT, plus your groundworker

Your groundworker strips the site and lays the Type 1 to level. We come in twice: first to lay the drainage on the stripped site, then, once the Type 1 is handed over to tolerance, to do the slabs.

  • Our part is about 20 + 14 working days, with your groundworker in between
  • The ground, the Type 1 and the hand-over between two contractors sit with you
  • Four invoices
Who does what
WorkOption AOption B
Site clearance, topsoil strip, the rubble stockpile over Unit 3AIMYour groundworker
Edge beam dig, muck-away, Type 1 laid and rolled to levelAIMYour groundworker
Stone access pad and pump standingAIMYour groundworker
Drainage: pipes, chambers, Hydro-Brake, soakaway, swale, sewer connectionsAIM, alongside the earthworksAIM, first visit, before the Type 1 (sewer connections on that visit if Scottish Water's consent and the sewer allow; otherwise a separate connection visit at £5,250)
Blinding, DPM, edge forms, steel, holding-down bolts, both poursAIMAIM, on Type 1 handed over to tolerance
Soft or wet ground under the slabsAIM, at the agreed ratesYour groundworker; we check the Type 1 at handover
Visits to siteOneTwo, with your groundworker in between
Time on siteAbout 24 working daysAbout 20 + 14 working days
InvoicesThreeFour: the first when the drainage is complete and air-tested, then as set out in the Option B quotation
Our price, excluding VAT£254,100£195,000 + your groundworker

Option B is £59,100 less than Option A. For a fair comparison, add your groundworker's price for everything Option B leaves to them: site clearance and strip, the Unit 3 stockpile, the edge beam dig and muck-away, the working space and its backfill, proof rolling and the Type 1 to +/-10 mm with BEC's sign-off, the stone access and pump standing, and protecting our drainage until we return. Option B also carries our second mobilisation.

Why Option B takes longer, though it is less work for us. In Option A we run the whole site, so our drainage gang works alongside our earthworks gang and the slabs follow straight on: about 24 working days in one go. In Option B the drainage has to be in before your groundworker lays the Type 1, so nothing can overlap. We lay the drainage (about 20 working days) and leave, your groundworker does the earthworks and the Type 1, then we come back for the slabs (about 14 working days). Your groundworker's time sits between our two visits and is not in our figures, so the job as a whole runs longer than 34 working days.

Raft slabs and drainage, Units 1, 2 and 3
Quotation · AIM-Q-2026-1111-VTX01
Reference
AIM-Q-2026-1111-VTX01
Issued
11/11/2026
Valid for
30 days
Programme
About 24 working days
Price
£254,100 excl. VAT
Option A · we do it all

The price

£254,100
Lump sum · excluding VAT
Price £254,100 plus VAT
On site About 24 days
Payment Three invoices, 14 days
Valid 30 days
What you are paying for
ItemDescriptionAmount
01Preliminaries: set-up, welfare, fencing, services, access pad, travel
1 item
£27,875
02Site clearance and 300mm topsoil strip to the slab footprints
557 m²
£3,640
03Stockpile and beam dig, spoil away (39 loads), Type 1, blinding
462 m²
£52,050
04DPM, edge formwork, 16 sets of HD bolts (84) set to template
125 lm
£9,300
05Bar to preliminary BBS 14621/40/01 and 2 layers of A393 mesh
4.48 t + 362 m²
£29,540
06Unit 1 raft: RC35 pumped, power floated, cured
70.9 m³
£30,135
07Units 2 and 3 raft: RC35 pumped, power floated, cured
29.0 m³
£10,805
08Drainage to DBA SK-01: SW, foul, chambers, soakaway, swale
137 + 32 m
£90,755
Total, excluding VAT£254,100

Lump sum for the work described. Soft spots, over-dig and any build-up to formation are measured at the rates for changes.

What is and is not included

Included
  • Preliminaries: set-up, welfare, fencing, services, access pad, travel
  • Site clearance and 300mm topsoil strip to the slab footprints
  • Stockpile and beam dig, spoil away (39 loads), Type 1, blinding
  • DPM, edge formwork, 16 sets of HD bolts (84) set to template
  • Bar to preliminary BBS 14621/40/01 and 2 layers of A393 mesh
  • Unit 1 raft: RC35 pumped, power floated, cured
  • Units 2 and 3 raft: RC35 pumped, power floated, cured
  • Drainage to DBA SK-01: SW, foul, chambers, soakaway, swale
Excluded
  • Floor insulation, screed, finishes; soil stacks and plumbing above the slab
  • Yard, parking, footpaths, external works, and forming the site access
  • Felling trees, stumps and root balls (root voids at the soft-spot rate)
  • HD bolt and template supply, resin anchors, grouting, steelwork, D49 wrap and encasement
  • Any design: earthworks, formation, gas, beam sleeves (14621-50 general note 2)
  • Soft spots, wet ground, pumping, fill; extra dig if insulation goes under (rates for changes)
  • Contaminated spoil; extra made ground; SW fees and adoption; sewer or watermain diversion
  • TM and road or footway permits for vehicles, the pump, skips or fencing
  • South wall support or survey; inspections; tests beyond cubes and drain air tests
Weekend working
To suit our resource programme, we may carry out some of the work at weekends, for example where the next availability for a particular resource type falls on a Saturday or Sunday. This keeps your job moving and there is no extra charge for it. If you would rather we did not work weekends, just let us know when you accept the quote and we will plan around it. Please note that if the job is programmed to start within 30 days of your acceptance, ruling out weekends may delay the programme, depending on weekday availability. Where you ask us to work a weekend, an uplift applies to the labour for that work: 50% on Saturdays and 100% on Sundays.

How the work runs

WhenWhat happensWho
Week 1Set up, services, strip, dig the edgesAIM
Week 2Proof roll, Type 1, DPM, formsAIM, BEC check
Week 3Steel, mesh, HD bolts, pour Unit 1AIM
Week 4Pour Units 2 and 3, strike, hand overAIM

Before we start

What we need from you
RFI-001 · Retaining wall
How deep is the south retaining wall founded, who owns it, and is there a condition survey? The edge beams go about 0.7 m below its toe, 1 to 1.4 m away.
RFI-002 · Scottish Water
Has Scottish Water's asset impact case DSCAS-0137051-PPW been closed, and is any DOMS approval needed before stripping near the watermain?
RFI-003 · Ground investigation
Is there a site investigation for the slab footprints? The structural spec refers to one; the pack has percolation tests only.
RFI-004 · Levels
Can you send the topographic survey in CAD, or existing levels under each slab? We have priced the stripped level as the slab formation.
RFI-005 · Topsoil
Can the topsoil be stockpiled on site for your landscaping rather than taken away? If so, where?
RFI-006 · Trees
How many trees are inside the slab footprints, and has anyone checked them for nesting birds or a TPO?
RFI-007 · Principal contractor
Who is principal contractor for the build, and who runs the site while we are on it? Steel erection, brickwork and cladding follow us.
RFI-008 · Access and deliveries
Is the site clear and open for a 14 t excavator, an 8-wheel tipper, ready-mix wagons and a boom pump from Newark Street?
RFI-009 · Programme and terms
What start date are you working to, and are you content with the payment terms in the quotation (three invoices, 14 days, no retention)?
Technical queries
TQ-001 · Structural / Architectural
Does the floor insulation go under the slab (14621-01 Rev C detail) or on top under the 100 mm screed (25-038-BW-002 Rev B)?
The two drawings disagree.
TQ-002 · Structural
Is BEC content with each raft as one monolithic pour, slab and edge beams together, with no construction joint?
14621-01 Rev C notes ask for the casting sequence and CJ positions to be agreed.
TQ-003 · Structural
What thickness of Type 1 does BEC want under the raft and the beams?
The notes give the spec (SHW 803), not the thickness.
TQ-004 · Structural
Is any gas protection needed under the slabs?
14621-50 lists gas preclusion as performance-specified.
TQ-005 · Structural
Drawing 40 note 10 refers to bar schedules BBS 12687-21-01, but the schedule issued is 14621/40/01 marked Preliminary. Which governs, and when is the construction issue due?
Bar quantity and order.
TQ-006 · Steelwork
Will the steelwork supplier provide the HD bolts and templates for us to cast in? And will the erector post-fix the resin anchors to the UC and PFC posts and grout the baseplates?
14621-50: 'Contractor is responsible for all cast-in fixings'.
TQ-007 · Architectural
If the 100 mm screed goes on top, do you still want a power-floated finish to the slab?
A screed would not need it.
TQ-008 · M&E
Are there any ducts, drains or sleeves through or under the slabs, and who places them before we pour?
The BW drawing shows ducting to an internal termination point.

Rates for changes

What a change costs
ItemRate
Labour, per day
Foreman£385
Skilled operative£280
Labourer£196
Plant and materials on instructionCost + 15%
Ground
Soft spots, root voids or extra dig, dug and carted away (inert), per m³£90
Replaced with GEN1 concrete, per m³£230
Fill to formation, placed and rolled, per m³£105
Each load of spoil more or less, inert£460
Each load of spoil more or less, mixed rubble£630
Concrete and steel
Extra RC35 placed, per m³£230
Bar supplied and fixed, per tonne more or less£1,950
Each extra pour or construction joint£4,250
Drainage, each more or less
150 surface water pipe, per m£65
600 inspection chamber£890
1200 manhole£2,130
Soakaway crate, per m³£300
Connection to the public sewer£1,750
Options
Topsoil kept on site, not carted awayLess £8,740
Tamped finish in place of power floatLess £2,400

Changes are agreed in writing before the work, at these rates. Weekend working is set out in Section 02.

Download this quotation

Option B · from your Type 1

The price

£195,000
Lump sum · excluding VAT
Price £195,000 plus VAT
On site About 20 + 14 days
Payment Four invoices, 14 days
Valid 30 days
What you are paying for
ItemDescriptionAmount
01Preliminaries: set-up, welfare, fencing, road cleaning on pour days, travel
1 item
£17,665
02Handover check, sand blinding, 1200g DPM, edge formwork, 16 sets of HD bolts (84)
125 lm
£11,415
03Bar to preliminary BBS 14621/40/01 and 2 layers of A393 mesh
4.48 t + 362 m²
£28,990
04Unit 1 raft: RC35 pumped, power floated, cured
70.9 m³
£30,130
05Units 2 and 3 raft: RC35 pumped, power floated, cured
29.0 m³
£10,805
06Drainage, first visit before the Type 1: SW, foul, chambers, Hydro-Brake, soakaway, swale
137 + 32 m
£95,995
Total, excluding VAT£195,000

Lump sum on Type 1 handed over to the tolerance below.

What is and is not included

Included
  • Preliminaries: set-up, welfare, fencing, road cleaning on pour days, travel
  • Handover check, sand blinding, 1200g DPM, edge formwork, 16 sets of HD bolts (84)
  • Bar to preliminary BBS 14621/40/01 and 2 layers of A393 mesh
  • Unit 1 raft: RC35 pumped, power floated, cured
  • Units 2 and 3 raft: RC35 pumped, power floated, cured
  • Drainage, first visit before the Type 1: SW, foul, chambers, Hydro-Brake, soakaway, swale
Excluded
  • Site clearance, strip, stockpile removal, all dig and disposal, proof rolling, Type 1, working space and its backfill: by others
  • Stone access and the pump standing: by others
  • Floor insulation, screed, finishes; yard and external works; Scottish Water fees and adoption
  • Diversion of the public 225 sewer or the watermain; design of sleeves through edge beams
  • In the drainage dig: soft spots, wet ground, pumping, rock and obstructions (at the rates for changes)
  • HD bolt and template supply, resin anchors, grouting, steelwork, D49 wrap and encasement
  • Any design, including earthworks, formation and gas protection (14621-50 general note 2)
  • TM and road or footway permits for vehicles, the pump, skips or fencing
  • Engineer's inspections, testing other than cubes
Weekend working
To suit our resource programme, we may carry out some of the work at weekends, for example where the next availability for a particular resource type falls on a Saturday or Sunday. This keeps your job moving and there is no extra charge for it. If you would rather we did not work weekends, just let us know when you accept the quote and we will plan around it. Please note that if the job is programmed to start within 30 days of your acceptance, ruling out weekends may delay the programme, depending on weekday availability. Where you ask us to work a weekend, an uplift applies to the labour for that work: 50% on Saturdays and 100% on Sundays.

How the work runs

WhenWhat happensWho
First visitDrainage, chambers, soakaway, swaleAIM
BetweenType 1 laid to levelYour groundworker
Week 1Handover check, blinding, DPM, forms, start steelAIM, your groundworker
Week 2Steel, mesh, bolts, pour Unit 1AIM
Week 3Pour Units 2 and 3, strike, hand backAIM

Before we start

What we need from you
Q-01 · Question
Who is laying the Type 1, and when will it be ready to hand over?
Q-02 · Question
Does the insulation go under or on top of the slab?
Q-03 · Question
Who supplies the HD bolts and templates?
Q-04 · Question
Is the 225 sewer being diverted as shown on ST-002 Rev C, and who holds the Scottish Water consents?
Q-05 · Question
Can a boom pump stand inside the site within reach of the far end of Unit 1?
Q-06 · Question
Who is principal contractor, and what start date are you working to?
Technical queries

What we need handed over

Before our slab visit
  • Type 1 by others to SHW 803, compacted and trimmed to +/-10 mm of formation (8.98 Unit 1, 9.04 Units 2 and 3) and to the edge-beam profile on 14621-01 and 101
  • 500 mm working space dug outside the beam faces by others, and backfilled by others after we strike
  • BEC sign-off and compaction records handed to us before we start
  • A stone access and an 8 x 8 m plate-tested pump standing within reach of a 36 m boom, by others
  • One pour per raft; joints designed by BEC
  • Two visits: drainage first (about 20 days, on stripped ground, before your Type 1), then the slabs (about 14 days from a ready handover)

Rates for changes

What a change costs
ItemRate
Labour, per day
Foreman£385
Skilled operative£280
Labourer£196
Plant and materials on instructionCost + 15%
Ground in our drainage dig
Soft spots, root voids or extra dig, dug and carted away (inert), per m³£90
Replaced with GEN1 concrete, per m³£230
Each load of spoil more or less, inert£460
Each load of spoil more or less, mixed rubble£630
Type 1 handover
Type 1 not ready or out of tolerance: re-trim, standing or a return visitDay rates
Concrete and steel
Extra RC35 placed, per m³£230
Bar supplied and fixed, per tonne more or less£1,950
Each extra pour or construction joint£4,250
Drainage, each more or less
150 surface water pipe, per m£65
600 inspection chamber£890
1200 manhole£2,130
Soakaway crate, per m³£300
Connection to the public sewer£1,750
Options
Tamped finish in place of power floatLess £2,400

Changes are agreed in writing before the work, at these rates. Weekend working is set out in Section 02.

Download this quotation