Raft slabs and drainage, Units 1, 2 and 3, 14 Newark Street, Port Glasgow
Both options finish in the same place: two raft slabs with their thickened edge beams, power floated and ready for the steel, and the drainage to Dougall Baillie's layout. The difference is who does the groundwork before the concrete goes in.
We strip the site, clear the stockpile over Unit 3, dig the edge beams, lay and roll the Type 1, lay the drainage alongside, then pour both slabs.
Your groundworker strips the site and lays the Type 1 to level. We come in twice: first to lay the drainage on the stripped site, then, once the Type 1 is handed over to tolerance, to do the slabs.
| Work | Option A | Option B |
|---|---|---|
| Site clearance, topsoil strip, the rubble stockpile over Unit 3 | AIM | Your groundworker |
| Edge beam dig, muck-away, Type 1 laid and rolled to level | AIM | Your groundworker |
| Stone access pad and pump standing | AIM | Your groundworker |
| Drainage: pipes, chambers, Hydro-Brake, soakaway, swale, sewer connections | AIM, alongside the earthworks | AIM, first visit, before the Type 1 (sewer connections on that visit if Scottish Water's consent and the sewer allow; otherwise a separate connection visit at £5,250) |
| Blinding, DPM, edge forms, steel, holding-down bolts, both pours | AIM | AIM, on Type 1 handed over to tolerance |
| Soft or wet ground under the slabs | AIM, at the agreed rates | Your groundworker; we check the Type 1 at handover |
| Visits to site | One | Two, with your groundworker in between |
| Time on site | About 24 working days | About 20 + 14 working days |
| Invoices | Three | Four: the first when the drainage is complete and air-tested, then as set out in the Option B quotation |
| Our price, excluding VAT | £254,100 | £195,000 + your groundworker |
Option B is £59,100 less than Option A. For a fair comparison, add your groundworker's price for everything Option B leaves to them: site clearance and strip, the Unit 3 stockpile, the edge beam dig and muck-away, the working space and its backfill, proof rolling and the Type 1 to +/-10 mm with BEC's sign-off, the stone access and pump standing, and protecting our drainage until we return. Option B also carries our second mobilisation.
Why Option B takes longer, though it is less work for us. In Option A we run the whole site, so our drainage gang works alongside our earthworks gang and the slabs follow straight on: about 24 working days in one go. In Option B the drainage has to be in before your groundworker lays the Type 1, so nothing can overlap. We lay the drainage (about 20 working days) and leave, your groundworker does the earthworks and the Type 1, then we come back for the slabs (about 14 working days). Your groundworker's time sits between our two visits and is not in our figures, so the job as a whole runs longer than 34 working days.
| Item | Description | Amount |
|---|---|---|
| 01 | Preliminaries: set-up, welfare, fencing, services, access pad, travel 1 item | £27,875 |
| 02 | Site clearance and 300mm topsoil strip to the slab footprints 557 m² | £3,640 |
| 03 | Stockpile and beam dig, spoil away (39 loads), Type 1, blinding 462 m² | £52,050 |
| 04 | DPM, edge formwork, 16 sets of HD bolts (84) set to template 125 lm | £9,300 |
| 05 | Bar to preliminary BBS 14621/40/01 and 2 layers of A393 mesh 4.48 t + 362 m² | £29,540 |
| 06 | Unit 1 raft: RC35 pumped, power floated, cured 70.9 m³ | £30,135 |
| 07 | Units 2 and 3 raft: RC35 pumped, power floated, cured 29.0 m³ | £10,805 |
| 08 | Drainage to DBA SK-01: SW, foul, chambers, soakaway, swale 137 + 32 m | £90,755 |
| Total, excluding VAT | £254,100 |
Lump sum for the work described. Soft spots, over-dig and any build-up to formation are measured at the rates for changes.
| When | What happens | Who |
|---|---|---|
| Week 1 | Set up, services, strip, dig the edges | AIM |
| Week 2 | Proof roll, Type 1, DPM, forms | AIM, BEC check |
| Week 3 | Steel, mesh, HD bolts, pour Unit 1 | AIM |
| Week 4 | Pour Units 2 and 3, strike, hand over | AIM |
| Item | Rate |
|---|---|
| Labour, per day | |
| Foreman | £385 |
| Skilled operative | £280 |
| Labourer | £196 |
| Plant and materials on instruction | Cost + 15% |
| Ground | |
| Soft spots, root voids or extra dig, dug and carted away (inert), per m³ | £90 |
| Replaced with GEN1 concrete, per m³ | £230 |
| Fill to formation, placed and rolled, per m³ | £105 |
| Each load of spoil more or less, inert | £460 |
| Each load of spoil more or less, mixed rubble | £630 |
| Concrete and steel | |
| Extra RC35 placed, per m³ | £230 |
| Bar supplied and fixed, per tonne more or less | £1,950 |
| Each extra pour or construction joint | £4,250 |
| Drainage, each more or less | |
| 150 surface water pipe, per m | £65 |
| 600 inspection chamber | £890 |
| 1200 manhole | £2,130 |
| Soakaway crate, per m³ | £300 |
| Connection to the public sewer | £1,750 |
| Options | |
| Topsoil kept on site, not carted away | Less £8,740 |
| Tamped finish in place of power float | Less £2,400 |
Changes are agreed in writing before the work, at these rates. Weekend working is set out in Section 02.
| Item | Description | Amount |
|---|---|---|
| 01 | Preliminaries: set-up, welfare, fencing, road cleaning on pour days, travel 1 item | £17,665 |
| 02 | Handover check, sand blinding, 1200g DPM, edge formwork, 16 sets of HD bolts (84) 125 lm | £11,415 |
| 03 | Bar to preliminary BBS 14621/40/01 and 2 layers of A393 mesh 4.48 t + 362 m² | £28,990 |
| 04 | Unit 1 raft: RC35 pumped, power floated, cured 70.9 m³ | £30,130 |
| 05 | Units 2 and 3 raft: RC35 pumped, power floated, cured 29.0 m³ | £10,805 |
| 06 | Drainage, first visit before the Type 1: SW, foul, chambers, Hydro-Brake, soakaway, swale 137 + 32 m | £95,995 |
| Total, excluding VAT | £195,000 |
Lump sum on Type 1 handed over to the tolerance below.
| When | What happens | Who |
|---|---|---|
| First visit | Drainage, chambers, soakaway, swale | AIM |
| Between | Type 1 laid to level | Your groundworker |
| Week 1 | Handover check, blinding, DPM, forms, start steel | AIM, your groundworker |
| Week 2 | Steel, mesh, bolts, pour Unit 1 | AIM |
| Week 3 | Pour Units 2 and 3, strike, hand back | AIM |
| Item | Rate |
|---|---|
| Labour, per day | |
| Foreman | £385 |
| Skilled operative | £280 |
| Labourer | £196 |
| Plant and materials on instruction | Cost + 15% |
| Ground in our drainage dig | |
| Soft spots, root voids or extra dig, dug and carted away (inert), per m³ | £90 |
| Replaced with GEN1 concrete, per m³ | £230 |
| Each load of spoil more or less, inert | £460 |
| Each load of spoil more or less, mixed rubble | £630 |
| Type 1 handover | |
| Type 1 not ready or out of tolerance: re-trim, standing or a return visit | Day rates |
| Concrete and steel | |
| Extra RC35 placed, per m³ | £230 |
| Bar supplied and fixed, per tonne more or less | £1,950 |
| Each extra pour or construction joint | £4,250 |
| Drainage, each more or less | |
| 150 surface water pipe, per m | £65 |
| 600 inspection chamber | £890 |
| 1200 manhole | £2,130 |
| Soakaway crate, per m³ | £300 |
| Connection to the public sewer | £1,750 |
| Options | |
| Tamped finish in place of power float | Less £2,400 |
Changes are agreed in writing before the work, at these rates. Weekend working is set out in Section 02.