New Gully at the EV Bays
| Item | Description | Amount |
|---|---|---|
| 01 | Mobilisation, barriers and site set-up: one-off Charged once. The gang and van to site, Chapter 8 barriers and signage round the two EV bays and the working area, a signed pedestrian route, RAMS and permit to dig, and the clear-down at the end. We lift the grating on the existing gully and check it before we connect to it. Charged once, whatever the final scope. | £340 |
| 02 | New trapped gully in the EV bay corner, connected into the existing gully: 1 nr Services scan and hand dig round the charger and lighting cables, saw-cut and break out, a trapped concrete gully pot with a D400 ductile grating set to the low point, bedded and surrounded in concrete, a 150 mm connection of up to 6 m cored into the existing gully pot above its trap, backfilled in compacted layers, arisings removed. | £3,145 |
| 03 | Tarmac reinstatement AC 10 laid hot in two lifts to full depth, each lift rolled, and every cut edge sealed. One batch of material covers it. Bay lining is not included. | £1,170 |
| Total, excluding VAT | £4,655 |
This price is firm within the limits set out here. Up to 6 m of connection into the existing gully is included, and anything beyond that is £330 per metre. If the existing gully turns out to be failing when we check it, we stop before connecting and the works to that point are £1,400. There is no allowance in the figure for what your video cannot show, which is why those limits are stated rather than buried.
| When | What happens | Who |
|---|---|---|
| Before | RAMS and permit to dig to the club, charger isolation booked with your operator, skip, concrete and asphalt booked | Office |
| Day 1 am | Barriers and pedestrian route up, grating lifted and the existing gully checked, services scanned, trial holes hand dug | 2 man gang |
| Day 1 pm | Saw-cut, break out, excavate, set the new gully, pour the bed and surround, lay the pipe and core into the existing pot, backfill | 2 man gang + 1.5t excavator |
| Overnight | Concrete cures. The excavation is plated and the bays stay closed | — |
| Day 2 | Trim, tack, lay AC 10 in two lifts and roll each one, seal the joints, clear down and the skip away | 2 man gang + hot box |