Cable route civils, Bradley Fell Farm, Wylam
About 92 m of trench, stone store to house meter, along the line your survey marked. The yard, barn and drive are gravel over hardcore; the verge and garden are soft. Anything we find below ground that isn’t described in the quotation is extra.
| Item | Description | Amount |
|---|---|---|
| 01 | Set up on site, scan for buried services, mark out the route 1 item | £985 |
| 02 | Trench through the gravel yard, barn floor and drive, reinstated 49.1 lm | £4,225 |
| 03 | Trench in the soft verge by the concrete track, reinstated 21.8 lm | £1,065 |
| 04 | Trench through the shrub bed and under the garden wall 21.3 lm | £4,740 |
| 05 | Two building entries, two draw pits, ducts proved 1 item | £2,285 |
| Total, excluding VAT | £13,300 |
Civils only, ducts ready for your electricians to pull the cable. Lines 2 and 3 are remeasured for length at the rates in section 04. The rest is lump sum. Underground obstructions, including buried concrete, are not included: see section 05.
| When | What happens | Who |
|---|---|---|
| Before | Order, RAMS, materials | KMM, AIM |
| Day 1 | Travel, scan, mark out, clear the shrub strip, start the yard | AIM |
| Day 2 | Yard, barn and drive, gate pad, Type 1 and gravel back | AIM |
| Day 3 | Soft verge, shrub bed, garden wall crossing | AIM |
| Day 4 | Building entries, draw pits, prove ducts, photos, travel home | AIM |